By Turnkey Project Stockholm – Constance Ragell
You have asked three contractors to price your commercial renovation.
The quotations arrive.
One is noticeably cheaper than the others. At first glance, choosing it might seem like an easy way to reduce the construction budget. But before comparing the numbers, there is another question worth asking:
Are all three contractors actually pricing the same thing?
Construction quotations are built around a scope of work, drawings, specifications, quantities, assumptions and exclusions. If those differ between quotations, the final totals aren't necessarily directly comparable.
A lower quotation may genuinely represent better value or a more efficient way of delivering the project. But it may also contain a different specification, fewer included works, provisional amounts or assumptions that eventually need to be resolved.
In this Blog, we look at what to check when comparing construction quotations and why understanding what sits behind the number can be just as important as the number itself.
Start With the Scope, Not the Total
Imagine Contractor A submits a quotation for SEK 1.8 million and Contractor B submits one for SEK 2.1 million.
It is natural to look immediately at the SEK 300,000 difference.
But suppose Contractor B has included painting, waste removal, final cleaning and several electrical works that Contractor A has excluded.
You are no longer comparing SEK 1.8 million with SEK 2.1 million for the same work.
You are comparing two different scopes.
Before focusing on the total price, establish what each contractor believes they have been asked to deliver. The clearer the scope is before quotations are requested, the easier that comparison becomes.
What Has Actually Been Included?
A construction quotation should be read beyond the number at the bottom.
Depending on the project, some of the questions worth checking include:
- Is demolition included?
- Is removal and disposal of construction waste included?
- Are electrical works included?
- Who supplies the lighting?
- Is painting included?
- Which flooring has been priced?
- Are ceilings included?
- Is ventilation work included?
- Are plumbing works included?
- Is custom joinery included?
- Who supplies particular materials or equipment?
- Are protection and final cleaning included?
- Are drawings or project coordination included?
Not every question will apply to every project. The purpose is to understand where the contractor's responsibility begins and ends.
An item that isn't included hasn't necessarily been forgotten. It may simply be expected to be supplied by the client, landlord or another contractor.
That is why the quotation needs to be understood in the context of the whole project.
Look Carefully at Exclusions
Exclusions can be just as important as inclusions.
A quotation might state that electrical work is excluded. Another may exclude painting. A third may include both but exclude specialist lighting or joinery.
None of those approaches is automatically wrong.
The problem begins when an exclusion isn't noticed until later.
Suppose one quotation is SEK 100,000 cheaper but excludes a piece of work that will eventually cost approximately the same amount to procure separately. The apparent saving may disappear once the complete project scope is considered.
This is why we wouldn't recommend simply comparing the totals at the bottom of three quotations.
First, understand the differences between them.
What Assumptions Has the Contractor Made?
Sometimes the information needed to calculate a fixed price simply isn't available yet.
The contractor then has to make an assumption.
Perhaps an existing ceiling is assumed to remain. Maybe the quotation assumes work can take place during normal working hours. Perhaps existing electrical capacity is assumed to be sufficient, or the contractor has assumed that the landlord will carry out a particular piece of work.
These assumptions matter because if the actual conditions are different, the cost or programme may change.
When reviewing a quotation, therefore, ask:
What had to be assumed in order to produce this price?
The fewer unresolved assumptions there are, the clearer the commercial picture becomes.
Specifications Matter Too
Two contractors can both include flooring without pricing the same flooring.
The same applies to doors, lighting, sanitary fittings, ironmongery, tiles, paint systems, joinery and many other parts of a commercial renovation.
For example, one quotation might allow for a standard product while another prices the exact product specified by the designer. Both quotations say "flooring included", but the underlying material cost may be very different.
This is where drawings and specifications become particularly useful.
As we discussed in our article on Why Construction Drawings Are So Important Before Building Starts, better information gives contractors a clearer basis for understanding what they are being asked to price.
The objective isn't to specify every screw before speaking to a contractor. It is to make sure important differences in quality and specification aren't hidden inside apparently similar descriptions.
Fixed Price, Allowance or Estimate?
Not every number appearing in a quotation necessarily has the same status.
Some items may be firmly priced based on a defined scope. Others may be allowances because a final product hasn't been selected or because the extent of the work cannot yet be established.
Imagine the client hasn't selected the final tiles. The quotation might contain an allowance for purchasing them. If the eventual selection costs more than the allowance, the project cost will change.
That doesn't make the original quotation misleading.
It means the allowance needs to be understood for what it is.
When comparing quotations, identify which amounts are based on defined work and which still depend on future decisions or information.
A Lower Price Isn't Automatically a Warning Sign
This distinction is important.
A contractor may legitimately be cheaper because they have lower overheads, a particularly efficient method, established suppliers, available resources or simply want the project more than another contractor does.
A low price therefore isn't evidence by itself that something is wrong.
There is an interesting parallel in Sweden's rules for public procurement. These rules do not govern an ordinary private commercial renovation, so they should not be treated as rules for choosing your own contractor. But the principle is useful: the Swedish National Agency for Public Procurement explains that where a public-sector tender appears abnormally low, the contracting organisation must, in certain procurements, ask the supplier to explain the price rather than simply assuming why it is low. Acceptable explanations can include particularly cost-effective methods, technical solutions or economies of scale. Upphandlingsmyndigheten – Onormalt låga anbud Upphandlingsmyndigheten
For a private client comparing construction quotations, the practical lesson is much simpler:
If one number is substantially different, understand why.
There may be a perfectly good explanation.
The Cheapest Quote and the Lowest Final Cost Are Not Necessarily the Same Thing
This is perhaps the most important distinction.
The quotation is the price offered for a particular understanding of the project at a particular point in time. The final construction cost is what the project ultimately costs after the actual scope, selections, site conditions and changes have been dealt with.
A quotation with a clearly defined scope can therefore sometimes give a client greater budget visibility than a lower quotation containing substantial unknowns. That doesn't mean you should automatically choose the higher quotation.
It means price needs context.
When quotations differ, understand whether the difference comes from efficiency, specification, scope, exclusions, assumptions, allowances or something else.
Only then are you in a much better position to understand what each contractor is actually offering.
Comparing Quotes for a Commercial Project in Stockholm?
If you are planning an office renovation, retail fit-out or another commercial construction project in Stockholm, getting quotations is only one part of establishing the construction budget.
The scope, drawings and specifications behind those quotations matter too.
Turnkey Project Stockholm can assist with project planning, drawings, budgeting, contractor coordination and construction delivery, helping establish clearer information before work begins.
The question isn't only: “What does it cost?”
It is also: “What exactly are we getting for that price?”
Sources & References Behind This Blog
Svenska sammanfattningar av våra artiklar finns på vår svenska bloggsida
For further reading on tender evaluation and understanding unusually low prices:
- Upphandlingsmyndigheten – Onormalt låga anbud
Official guidance from Sweden's National Agency for Public Procurement explaining the rules around abnormally low tenders in public procurement and why a low price may require explanation rather than assumption.
Read at Upphandlingsmyndigheten Upphandlingsmyndigheten - Upphandlingsmyndigheten – Anbudsprövningen
Official guidance explaining how tenders in public procurement are checked against the requirements established in the procurement documents.
Read at Upphandlingsmyndigheten Upphandlingsmyndigheten
Important context: These sources concern Swedish public procurement under LOU/LUF. The article uses them only where explicitly identified as a comparison; they are not presented as legal rules governing an ordinary private commercial renovation.